Recently the German company Bauer contracted to lay the foundation for the Kingdom Tower finished its work the company reports.

The work involved installing very long piles deep into the desert ground.

Thus 72 piles that were 1.5 meters in diameter were laid at a depth of 110 meters another 154 piles at various depths and another 44 piles of 1.8 diameters were laid 50 meters deep.

After this initial phase of the construction work is over it is expected that we will see the tower rise from the ground soon although there are no reports about the construction’s schedule.